CE Management Report September 2021

BALLYBRACK CYCLE SCHEME Work ongoing on detailed design. Ground investigation underway.

PEDESTRIAN SAFETY INTERVENTIONS 2019 (€500K) Construction completed. Project closeout is underway.

PEDESTRIAN SAFETY INTERVENTIONS 2020/ 2021 Construction is completed on Rathmore Road, Ringmahon Road, Vicar’s Road and Dublin Hill. Contractor appointed for St. Patrick’s Road, Alderbrook in Frankfield and Popham’s Road as one contract and construction to commence in October. NORTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT Route Options sifting is advancing. Discussions ongoing with adjoining developers/landowners re. SHD’s an d requirements for set aside lands. Discussions ongoing with NTA regarding the Strategic Assessment Report (SAR). Formal submission of SAR to NTA, Department of Transport & DPER in the coming weeks.

SOUTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT Route option identification is ongoing.

CURAHEEN TO CARRIGROHANE FOOTPATH AND CYCLE PATH UPGRADE C onstruction is ongoing.

CURRAGH RD/ PEARSE ROAD JUNCTION UPGRADE SCHEME Work ongoing on detailed design.

BLARNEY VILLAGE CYCLE ROUTE Procurement of consultant is underway.

LEE TO SEA CYCLE ROUTE STUDY Preparation of documents to appoint consultant is underway and will be advertised in October.

MAYFIELD TO GLEN CYCLE ROUTE Route option assessment is continuing.

DOUGLAS TO GRANGE BRIDGE Tender process to appoint consultant is underway.

DONNYBROOK HILL PEDESTRIAN UPGRADE SCHEME Detailed Design is ongoing.

STREETSCAPE RENEWAL OF COOK STREET, PRINCES STREET AND MARLBORO STREET Tender process for appointment of consultant for prelim design is underway. Roads Capital Programme: CCC Funded Projects ST MARY’S CAMPUS Works completed. Project close out ongoing. HARBOUR VIEW ROAD JUNCTION UPGRADE JUNCTION Construction is ongoing. Funding has been received from NTA to upgrade to footpath on Blarney Road and construction is underway. Roads Capital Programme: DTTS & CCC Funded Projects CORK SCIENCE & INNOVATION PARK ROAD PROJECT Land acquisition process is complete. Detailed Design and preparation of construction contract documents for Phase 1A is complete. Contract is ready to go to tender. Roads Capital Programme: LIHAF Funded Projects DOCKLANDS TO CITY CENTRE PROJECT (€6.5 million) Detailed design process underway. Legal Team review of documents is complete. Design team revising documents as per Legal Team advice. Revised Part 8 publication by years end. GLANMIRE ROADS IMPROVEMENT SCHEME Compulsory Purchase Order has been confirmed by An Bord Pleanala, Notice to Treat was issued in August for landowners for the first package of works. Notice of Entry was issued in September. Procurement of a contractor for this work package is underway. Section 50 applications for new bridges are awaiting OPW approval and detailed design is continuing. A Section 38 consultation for alternative Cycle route connecting Rivertown to Glanmire Community College has been approved by Council. MONAHAN ROAD EXTENSION (€5 million) Preliminary design is complete. Land Acquisition requirements have been confirmed. Site Investigation contract is complete. Part 8 planning process is underway. Fencing contract procurement underway. Urban Regeneration & Development Fund

DOCKLANDS TRANSPORT INFRASTRUCTURE (URDF) Programme delivery strategy and expenditure profile are under development.

BEAMISH & CRAWFORD QUARTER INFRASTRUCTURE The appraisal process for the selection of the bridges at Proby’s Quay and Crosses Green is com plete. Detailed design for the public realm enhancement of South Main Street, Tuckey Street, Proby’s Quay, Sullivan’s Quay, etc. is complete. Part 8 planning process is underway. Construction tender to commence in early 2022.

MARINA PARK PHASE 2 Design Team appointed. Preliminary design process is underway.

NEW HORGAN’S ROAD (NORTH DOCKS) Tender documents for the selection of a design team are under development

Bridge Repair and Rehabilitation Projects DALY’S BRIDGE: Project close out is underway.