CE Management Report September 2021

BANNOW BRIDGE, GRANGE ROAD BRIDGE, BLACKSTONE BRIDGE & HEALY’S BRIDGE Project close out is underway.

PRINCIPAL INSPECTIONS OF BRIDGE AND CULVERT STRUCTURES WITHIN CORK CITY BOUNDARY 2020 Project completed.

PARLIAMENT BRIDGE : (North-west wing wall - partial collapse of a section of the masonry buttress, exposed and dislodged backfill material, substantial bulge in the masonry façade) Project completed.

GLYNTOWN BRIDGE, CLASH ROAD BRIDGE, MYRTLE HILL BRIDGE, FOURMILE BRIDGE, WYSE ’S BRIDGE & HOLLYMOUNT JUNCTION CULVERT Tenders returned and under evaluation leading to the appointment of a consultant.

CARRIGROHANE BRIDGE Preparation of documents commenced leading to the appointment of a consultant.

New Cycle Lanes HORGANS QUAY Construction of the inbound cycle lane is complete. Road Safety Audit & Final Account discussions ongoing.

CENTRE PARK ROAD Construction of the outbound cycle lane is complete.

MONAHAN’S ROAD Construction of the inbound cycle lane is complete.

SOUTH MALL Construction of two-way cycle lanes and related street repairs is complete. Planter installation scheduled for December.

VICTORIA ROAD, ALBERT QUAY & TERENCE MACSWINEY QUAY Construction is complete. Minor additional scope will be undertaken in the coming weeks.

DONOVAN’S ROAD, COLLEGE ROAD, MAGAZINE ROAD TO GLASHEEN LINK Donovan’s Rd and College Rd are complete. Contractor is working on the Glasheen and Magazine Link.

MELBOURN ROAD AND ROSSA AVENUE Construction of cycle lanes are substantially complete.

KNAPP’S SQUARE CYCLE AND PEDESTRIAN UPGRADES Section 38 was approved by Council in September. Detailed Design is underway.