CE Management Report April 2021

GLANMIRE TO CITY CYCLE NETWORK (Phase 1 Glanmire to Dunkettle) Tender brief and related tender documents are under development for the appointment of the Design Team. MAHON TO CITY CENTRE TRANSPORT CORRIDOR will be delivered as part of bus connects.

EXISTING NORTHERN RING ROAD ENHANCEMENT PROJECT will be delivered as part of bus connects.

SOUTH QUAYS PUBLIC TRANSPORT IMPROVEMENT SCHEME Option assessment is ongoing.

GRANGE TO TVP PEDESTRIAN & CYCLEWAY inc. N40 Bridge detailed design and preparation of tender documentation is ongoing. Compulsory Acquisition Oder lodged with An Bord Pleanala for required land acquisition.

SOUTH DOUGLAS ROAD JUNCTION work ongoing on detailed design and preparation of tender documentation for appointment of contractor is commenced.

BALLYBRACK CYCLE SCHEME work ongoing on detailed design. PEDESTRIAN SAFETY INTERVENTIONS 2019 (€500K) construction completed. Project closeout is underway.

PEDESTRIAN SAFETY INTERVENTIONS 2020/ 2021 Construction is now ongoing on Ringmahon Road and vicar’s road and Dublin Hill and will commence shortly on Rathmore Road. Detailed design underway for St. Patrick’s Road and Alderbrook in Frankfield. Preparation of section 38 documentation is underway at Popham’s Road NORTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT Design Team appointed for the route selection assessment. Route Options sifting is advancing. Discussions ongoing with adjoining developers/landowners re. SHD’s and requirements for set aside lands.

SOUTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT Data collection and route selection assessment ongoing.

CURAHEEN TO CARRIGROHANE FOOTPATH AND CYCLE PATH UPGRADE C onstruction has recommenced on Carrigrohane to Model farm Road section. CURRAGH RD/ PEARSE ROAD JUNCTION UPGRADE SCHEME. Part 8 Planning is out for Public Consultation. Appointment of design team for detailed design is underway.

BLARNEY VILLAGE CYCLE ROUTE Preparation of documents to appoint consultant is underway.

LEE TO SEA CYCLE ROUTE STUDY Preparation of documents to appoint consultant is underway.

MAYFIELD TO GLEN CYCLE ROUTE Preparation of documents to appoint consultant is underway.

DOUGLAS TO GRANGE BRIDGE Preparation of documents to appoint consultant is underway.

DONNYBROOK HILL PEDESTRIAN UPGRADE SCHEME . Appointment of design team for detailed design is underway.

STREETSCAPE RENEWAL OF COOK STREET, PRINCES STREET AND MARLBORO STREET Tender documents for the selection of multidisciplinary design team is under development. Roads Capital Programme: CCC Funded Projects: ST MARY’S CAMPUS works completed. Project close out ongoing. HARBOUR VIEW ROAD JUNCTION UPGRADE JUNCTION Construction has recommenced following temporary suspension due to Covid Level 5 restrictions. Roads Capital Programme: DTTS & CCC Funded Projects: CORK SCIENCE & INNOVATION PARK ROAD PROJECT Land acquisition process is complete. Detailed Design and preparation of construction contract documents for Phase 1A is complete. Contract is ready to go to tender. Roads Capital Programme: LIHAF Funded Projects : DOCKLANDS TO CITY CENTRE PROJECT (€6.5 million) Detailed design process underway. Revised planning documents are under review by Legal Team. GLANMIRE ROADS IMPROVEMENT SCHEME Compulsory Purchase Order has been submitted to An Bord Pleanala, Oral Hearing took place on 27 th January, response awaited. Section 50 applications for new bridges are awaiting OPW approval and detailed design is continuing. Construction contract documents for the first package of works is under development. A section 38 consultation for alternative Cycle route connecting Rivertown to Glanmire Community College is underway. MONAHAN ROAD EXTENSION (€5 million) Design Team has been appointed. Preliminary design work is underway. Land Acquisition requirements have been confirmed. Site Investigation contract is complete. Part 8 planning process will commence in May.